3 INSTALLATION 3.1 TRANSPORT Transport UPS only in upright position! The UPS is packaged on a pallet suitable for handling with a forklift. Pay
3.2 DELIVERY When delivered, inspect the package integrity and the physical conditions of the cabinets carefully. In case of any damage sustained d
3.4 PLACE OF INSTALLATION 3.4.1 UPS location WARNING ! A QUALIFIED ELECTRICAL CONTRACTOR must carry out the installation and cabling of the UPS.
Openings for input and output cable connections SGS_225-300_S2_UPS view top_01US1,650mm64.96"160mm6.30"2.76"40mm1.58"70mm31.50&quo
UPS3 - 4 - 5 - 6SGS_225-300_S2_RPA disposition_GE_01USUPS 1UPS 2 Fig. 3.4.1-5 RPA system disposition In case of parallel system, try to place the
3.5 VENTILATION AND COOLING Fig. 3.5-1 Installation on plain floor Fig. 3.5-2 Installation on raised floor The heat produced by the UPS is t
3.6 UNPACKING The UPS and Battery Cabinets may be shipped packaged in carton boxes or in wooden crates (if requested). Move the cabinets as close as
3.7 ELECTRICAL WIRING WARNING ! UPS installation and connection must be performed by QUALIFIED SERVICE PERSONNEL ONLY. It is the responsibility of
3.7.2 Input/output over current protection and wire sizing The cabling of the UPS system has to be sized according to the UPS power rating. Sizing o
3.7.3 Battery over current protection and wire sizing NOTE ! • Please read the safety precautions at the front of this guide carefully, and thorou
Modifications reserved Page 2/40 OPM_SGS_ISG_M22_M30_2US_V010.doc Installation Guide S G S er i e s 22 5 & 300 UL S2 Model: SG Series 225 &
NEC SECTION 210-20 (a) Table 310-16. Allowable Ampacities of Insulated Conductors Rated O Through 2000 Volts, 60°C Trough 90°C (140°F Trough 194°F) N
3.8 WIRING CONNECTION WARNING! UPS installation and connection must be performed by QUALIFIED SERVICE PERSONNEL ONLY. 3.8.1 Power connections I
CAUTION ! Panels “A, B, C, D, E and F” should never be removed or replaced with power applied to the UPS. This panel is in close proximity to 480V li
3.8.2 Power connection with common input utility SGS_225-300_S2_UPS connection common_GE_01USAAPEInput utilityPE LoadLOADNL3L2L1NL3-1L2-1L1-11 - INP
NOTE ! This UPS is only designed to operate in a wye-configured electrical system with a solidly grounded neutral. The UPS cannot be operated from a
3.8.3 Power connection dual input utility (option) APE LoadPEInput utilityL1LOADL2L3NPE LoadPE Input utility1 - INPUT RECTIFIERL2-1L3-1L1-1N - Bypas
NOTE ! This UPS is only designed to operate in a wye-configured electrical system with a solidly grounded neutral. The UPS cannot be operated from a
Notices for installation 12342431BR1SGSU_225-300_S2_UPS BR1-2-3_01BR2BR3Q20 OFFI ONQ20 OFFI ON0 OFFI ONQ118121316141517712346519811221021209 Fig. 3.8.
3.8.4 Battery and External Battery Breaker connection _+Q10 OFFI ONQ20 OFFI ONBATTERYPESGS_225-300_S2_UPS connection battery_01US1917186720982110221
3.8.5 Interface to External Bypass for single unit If the UPS system is equipped with an External Maintenance Bypass Switch, connect the NO (normall
Dear Customer, We thank you for selecting our products and are pleased to count you amongst our very valued customers at GE. We trust that the use
3.8.7 Setup for SG Series 225 & 300 intended to be operated in eBoost™ Operation Mode NOTE ! For systems intended to be operated in eBoost™ Op
3.9 RPA PARALLEL SYSTEM CONNECTION WARNING ! This operation must be performed by QUALIFIED SERVICE PERSONNEL ONLY before the initial start-up. ENS
3.9.2 Parallel control bus connection In cases of parallel operation, the communication between the units takes place through the control bus cables
JP3JP1JP4IM 0048JP2SGSU_225-300_S2_RPA-IM0048_02JB1JA1JP1 JP2JP4JP3JAJB Fig. 3.9.2-2 Bus connection on terminal units Terminal units On the paralle
3.9.3 Control bus cable location WARNING ! This operation must be performed by QUALIFIED SERVICE PERSONNEL ONLY before the initial start-up. ENSUR
Q1Q21234Q1Q2UPS 1UPS 2Next parallelunit 3, 4, 5, 6JA1JB1JAJBJB1JA1JA2JB2JA1JB1JBJAJB2JA234123412SGSU_225-300_S2_RPA control bus cable_03US121132514153
4 CUSTOMER INTERFACE 4.1 CUSTOMER INTERFACE Serial port J3 - RS 232 (sub D - female 9 pin) Modifications reserved Page 36/40 OPM_SGS_ISG_M22_M30_2U
4.1.1 Serial Port J3 SGS_225-300_Customer interface J3_0143211234J3 Serial port J3 - RS-232 (sub D, female 9 pin) that allows: Total remote managem
4.1.3 Programmable input free contacts Some programmable UPS functions (indicated in Section 8.1), can be activated by closing an external contact, i
4.1.7 EPO (Emergency Power Off) Input contact Be aware: The reliability of the system depends on this contact NC (Normally Closed)! An external E
Preface Congratulations on your choice of a SG Series Uninterruptible Power Supply (UPS). It will help eliminate load disturbances due to unexpected
Modifications reserved Page 40/40 OPM_SGS_ISG_M22_M30_2US_V010.doc Installation Guide SG S er i e s 2 25 & 30 0 UL S2 5 NOTES 5.1 NOTES FO
Table of contents Page 1 IMPORTANT SAFETY INSTRUCTIONS ...
Modifications reserved Page 6/40 OPM_SGS_ISG_M22_M30_2US_V010.doc Installation Guide S G S e r i e s 22 5 & 30 0 UL S2 1 IMPORTANT SAFETY INSTR
Safety instructions when working with battery EXTERNAL BATTERY MUST BE INSTALLED AND CONNECTED TO THE UPS BY QUALIFIED SERVICE PERSONNEL ONLY. INSTA
Safety symbols and warnings Safety warnings The text of this manual contains some warnings to avoid risk to the persons and to avoid damages to the
2 LAYOUT 2.1 LAYOUT SG Series 225 & 300 SGS_225-300_S2_UPS_GE_02 Fig. 2.1-1 SG Series 225 & 300 general view SGS_225-300_S2_UPS_030 OF
Commentaires sur ces manuels