g DEH-023 Installation Instructions MicroVersaTrip® Plus and MicroVersaTrip® PM Conversion Kits For Westinghouse® Types DS-206, DSL-206, DS-416
SECTION 4 INSTALLING THE CONVERSION KIT (CONTINUED) Wire Harness Connector Assembly and Installation The wire harness includes a 36-pin progr
SECTION 4 INSTALLING THE CONVERSION KIT (CONTINUED) Wire Harness Connector Assembly and Installation (Continued) Step 3. Slide the adapter br
SECTION 4 INSTALLING THE CONVERSION KIT (CONTINUED) Programmer Bracket Installation Step 1. Install the programmer bracket to the auxiliary s
SECTION 4 INSTALLING THE CONVERSION KIT (CONTINUED) Wire Harness Installation (Continued) A mounting plate is supplied with each hardware kit
Fig. 21. Programmer Installation SECTION 6 FOUR-WIRE GROUND FAULT OPTION The ground fault option in all four-wire systems requires an addition
SECTION 6 FOUR-WIRE GROUND FAULT OPTION (CONTINUED) Step 3. Step 2. Route the wire through the equipment and connect to the 2-pin connect
GROUND FAULT OPTION (CONTINUED) Fig. 23. Neutral Sensor Outline for DS-416, DSL-416 and DS-420 Breakers SECTION 6 FOUR-WIRE GROUND FA
17 Once the breaker has been converted, but before it is energized, it must be tested. See below for testing and troubleshooting details. Testing B
18 SECTION 7 TESTING AND TROUBLESHOOTING (CONTINUED) False Tripping Breakers Equipped with Ground Fault When nuisance tripping occurs on brea
(CONTINUED) Fig. 25. Cabling Diagram - MicroVersaTrip® Plus and MicroVersaTrip® PM with Ground Fault on 4-Wire Load 19
2 TABLE OF CONTENTS Page SECTION 1 GENERAL INFORMATION…………………………………………………………... 3 SECTION 2 PRIOR TO INSTALLATION…………………………………………………………… 3 SECT
20 These instructions do not purport to cover all details or variations in equipment nor to provide for e
3 SECTION 1 GENERAL INFORMATION GE Conversion Kit installation is straightforward, but does require careful workmanship and attention to these instr
SECTION 3 BREAKER PREPARATION Preparing a Westinghouse® DS type breaker (Fig. 1) for conversion consists of the following steps: 1. Removing th
SECTION 3 BREAKER PREPARATION (CONTINUED) Step 2. Separate the front escutcheon cover of the breaker by removing the charging handle knob, and f
SECTION 3 BREAKER PREPARATION (CONTINUED) Trip Actuator Disassembly The existing Westinghouse® trip actuator must be converted to the new MicroV
SECTION 4 INSTALLING THE CONVERSION KIT Installing the Phase Sensors (CT’s) Step 1. The CT’s slide onto the breaker’s primary load stabs in the
SECTION 4 INSTALLING THE CONVERSION KIT (CONTINUED) Flux Shifter Assembly, Adjustment and Installation The new MicroVersaTrip® flux shifter w
SECTION 4 INSTALLING THE CONVERSION KIT (CONTINUED) Flux Shifter Assembly, Adjustment and Installation (Continued) Step 3. Slide the actuator